How Long Does It Take To Get Plans Done?

Q. How long does it take to get plans done?

A. For an interior build-out a complete set of architectural plans takes an average of 6 - 8 weeks for your architect or designer to complete. It can take longer depending on how many revisions it takes to get your approval on the final drawings.

For a building it can take 4 months or more depending on how long it takes to get preliminary approvals on the site plan before the actual construction drawings can be started.